XC Maintenance Program: outline, connection and menu
Set up the XC maintenance program — the PC-based tool used to confirm XC status/error information or to control the XC independently — by gathering the required hardware, wiring it into either the gantry stationary section (for logs) or directly into the XC PWB (for full control), starting the communication program, and unlocking the maintenance program's locked test switch through its Menu.
Tools & parts
| Item | Part number | Qty |
|---|---|---|
| Personal Windows computer with RS-232C port (9-pin D-sub connector) | n/a in source (source gives "e.g., T-3100" as an example machine) | |
| Maintenance program (TME version) | n/a in source | |
| Maintenance cable (for use with GTS) | BSX77-1467 (Gr. 04 (15 m)) |
Safety
Hazard: Power stays ON to the gantry rotation section for the entire time the maintenance cable is connected directly to the XC PWB (CNN711)
Consequence: The cable, or a person, could be caught in the energized rotation section (source's own wording: "avoid anyone or the cable being caught in the rotation section")
Avoidance: Be extremely careful to keep the cable and anyone nearby clear of the rotation section for the whole time the maintenance cable is connected to the XC PWB; be sure to return JP1 from 2-3 back to 1-2 after completing the work
Full step-by-step for XC Maintenance Program: outline, connection and menu
All 1 steps are documented in the FSELIB Aquilion 16 (TSX-101A) service manual — re-authored, web-first, with the real figures from the source.
Open the full procedureRelated X-ray & HV (XC control) guides
Source: 2D201-064E*H p.97. Preview re-authored by FSELIB — the full procedure with figures and steps is in the paid service manual.