GE Healthcare · CTLightSpeed26010100626000151450004260101046
LightSpeed 5.X (60kW)
Symptom
Scan aborts WITH Communications with the CCB sub-system has not been established. Scan aborts WITH Communications with the CCB sub-system has not been established
Error message
Error: 260101006 The CCB has failed to respond to an exception in the allotted time Fri Sep 8 07:32:31 2006 Error: 260101006 Host: orp Process: orp_subsys File: rcib_except_state.c Line: 269 Fri Sep 8 07:32:29 2006 Host : On-Board Rotating Processor Ermes # : 260101006 Exception Class : Soft Severity : Pri/Soft File : rcib_except_state.c Line# : 269 Function : No System Function Reported Scan Type : None/Unknown Scan: 0/0/0 The CCB has failed to respond to an exception in the allotted time. A reset of the controller may be required. Notification group number: 1 Notification group level: 8 Error: 260001514 RCIB Bus: Fault Line Interrupt Occurred. Timeout Waiting for Host Response to Fault Line Verification. See long description for full error Wed Apr 27 01:00:51 2005 Error: 260001514 Host: orp Process: orp_subsys File: notiftsk.c Line: 1368 Running: System Reset Wed Apr 27 01:00:51 2005 Host : Das Ermes # : 260001514 Exception Class : Abort Severity : Secondary File : notiftsk.c Line# : 1368 Function : No System Function Reported Scan Type : None/Unknown Scan: 50004/1/0 RCIB Bus: Fault Line Interrupt Occurred. Timeout Waiting for Host Response to Fault Line Verification. (Timeout:5
Applies to
- Models
- LightSpeed
- Product
- LightSpeed 5.X (60kW) LightSpeed 5.X (60kW) ~ Use with MDAS or GDAS HP_P_G4 HP_P_G8 HP_P_G16 HP_P_M16 LightSpeed 5.X 60KW G-DAS16 with GRE Links to the updated Product Service Manuals, FMIs, Service Notes, Option Manuals and Operator Documents can be found online at the attached sites. Always use the most appropriate documentation for your system.
- Component
- 2159578-3 collimator control board used on 1X/2X/3X/4X/5X See Long description for details Part #: 2159578-3 Part Type: GP CONSUMABLES Part Weight: 2.18 LBR Repairable: No Returnable: No Hazardous Material: N Description: COLLIMATOR CONTROL BOARD FRU: Yes Status: Orderable Comments: Not Available
- Area
- CT
Full cause & step-by-step resolution
The complete cause analysis, the step-by-step remedy and the attached service documents for this GE Healthcare CT issue are available to FSELIB subscribers — re-authored, web-first, searchable.