When Infinia Gantry rotated, UPS would change to by passed, and recover after rotation, and UPS eventually failed
Symptom
When Infinia Gantry rotated, UPS would change to by passed, and recover after rotation, and UPS eventually failed When Infinia Gantry rotated, UPS would change to by passed, and recover after rotation, and UPS eventually failed. Contributor 305012474 Qin June 11 2008
Applies to
- Models
- Infinia, Optima, Xeleris
- Product
- Infinia II Infinia II Acquisition System Infinia HE4 Infinia II Hawkeye 4 & Infinia II GP (Infinia running Windows XP software) Infinia I Infinia I Acquisition System
- Component
- *Power and Grounding Power and Grounding Includes: UPS types and service, P&P Audit procedures, P&P Troubleshooting Power and Grounding Includs UPS types Audit procedures Troubleshooting PQ Team Support Central: http://supportcentral.ge.com/products/sup_products.asp?prod_id=16313
- Area
- Nuclear Medicine
Full cause & step-by-step resolution
The complete cause analysis, the step-by-step remedy for this GE Healthcare Nuclear Medicine issue are available to FSELIB subscribers — re-authored, web-first, searchable.
7-day free trial · no credit card required
Related GE Healthcare Nuclear Medicine issues
- Part number needed for Optima E-Stop
- Service Note 43783_1 Feb/08 Infinia/Ventri/Xeleris 1.1 & 2
- Xeleris 1.1 DVD-RAMs do not always load back on to the same system that created them
- Unable to display or transfer Xeleris patient data.
- How to restore/install Entegra/Xeleris Aladdin protocols
- After software upgrade FMI40786, the Infinia application does not automatically start on boot up